Commercial Centre Settevalli,
Perugia (IT) |
 |
|
 |
| Key data |
| Owner: |
Commerciale Immobiliare Balanzano Srl |
 |
| Building type: |
Commercial Centre |
 |
| Case: |
New build |
 |
| Architect: |
Arch. Paolo Lucciconi, Italy |
 |
| Engineer: |
OIKOS PROGETTI, Foligno, Italy |
 |
| Contractor: |
S.E.A. Società Edile Appalti Spa, Marciano, Italy |
 |
| Technical data |
| Cobiax system: |
CBLM |
 |
| Slab thickness: |
47 and 45 cm |
 |
| Ball diameter: |
36 cm |
 |
| Span: |
12,50 m |
 |
| Total surface: |
about 3'200 m² |
|
 |
|
|
|
| |
Initial situation |
| |
Due to the irregular pattern of the supporting structure and the oval opening in the centre of the second floor, a steel construction was initially planned to be built with a tight interlacing of steel beams. |
| |
| |
Solution |
| |
The cobiax flat slab in Linked Cage Modules CBLM is built on site on DOKA formworks and allows the complete elimination of the steel beams. Thanks to the factory pre-assembly of the modules the production time can be reduced to a minimum. The two floors of a total of 3200 m2 were executed within 2 months. |
| |
| |
Conclusion |
| |
In view of the distinctiveness of the building with an exposed perimeter steel beam between the first and the second floor on about 6 m height, the lightweight flat slab solution of cobiax has been crucial for an optimised realisation especially considering the new seismic standards. |
| |
|
|
|
| |
|
|
|
|